Roadside safety features such as luminaire poles and sign supports have been subjected to crashworthiness evaluations using a variety of impact test specifications or guidelines. The current guidelines, outlined in the Manual for Assessing Safety Hardware (AASHTO 2016), provide guidance for evaluating breakaway luminaire poles, sign supports, and work-zone traffic control devices. To meet the requirements of Test Level 3 (TL-3), which is the most commonly used test level, three full-scale crash tests are necessary for each device. The FHWA currently requires that systems successfully complete the entire crash testing matrix to receive an FHWA eligibility letter.
Due to the many variations of luminaire poles, sign supports, and work-zone traffic control devices and the cost to certify them, MASH crashworthiness evaluations and product innovation have stagnated for some of these devices. Efforts under NCHRP Project 03-119 and NCHRP Project 22-43 have identified thousands of such devices and raised concerns about their crash safety performance. However, the requirement to conduct three full-scale crash tests for each device variation poses a significant burden for the FHWA, state departments of transportation (DOTs), and manufacturers of proprietary hardware. Highway agencies are faced with major workload and budget issues when trying to provide assurance that roadside devices meet safety requirements, all of which are complicated by limited inventories of such devices.
While NCHRP Project 03-119 investigated MASH compliance of the most prevalent roadside safety items within the three categories of sign supports, breakaway poles, and work-zone devices, NCHRP Project 22-43 was to determine whether families of systems can utilize a reduced test matrix for each design variation. To evaluate sign supports, breakaway luminaire poles, and work-zone traffic control devices to MASH standards while continually improving systems, it is desired to revise MASH with additional guidelines on selecting a critical test matrix for evaluating a family of devices.
NCHRP Project 22-43 has established a family of devices and developed testing protocols for the evaluation of each family defined within the three groups of sign supports, breakaway poles, and work-zone traffic control devices. For this study, the research team proposed organizing the systems into families within each of the three categories using a new definition for a “family of devices,” which was defined as follows:
A family of devices is a group of roadside safety devices that possess (1) at least one identical, critical, structural feature; and (2) possess a range of parameters that provide similar safety performance under MASH impact conditions.
Given the many critical features within each device category combined with the many variations in each device’s characteristics, this investigation would require an indefinite number
of simulations on thousands of families of devices. For the current project, the research team worked with the panel members to select a sample of families of common devices for which the analytical and physical testing program would be investigated. Given the available time and budget, the two most common categories were selected and approved by the panel for evaluation: (1) a breakaway steel luminaire pole with an aluminum TB1-17 frangible transformer base, and (2) a single 2¼-in., 12-gauge perforated square steel tube (PSST) sign support.
The original objectives of this research were to develop guidelines for the implementation of, and proposed modifications to, the MASH requirements for sign supports, breakaway poles, and work-zone traffic control devices, and to provide examples to demonstrate the application of the proposed guidelines. These objectives were further clarified to note that the efforts are anticipated to define sample families of devices that share similar characteristics that may influence crashworthiness.
Taking into account the time and budget constraints, the panel approved the evaluation of the two most common categories: (1) a breakaway steel luminaire pole with an aluminum TB1-17 frangible transformer base, and (2) a single 2¼-in., 12-gauge PSST sign support. Throughout this project, the research team benefited from the results of efforts under NCHRP Project 03-119, for which the research team is also the contractor.
This research was completed through the proposed research tasks and the four-phased approach.
Phase I of the project, which concluded in March 2021, encompassed multiple research activities related to the initial setup of the project, reviewed the existing research, and proposed analytical and physical testing programs to be conducted in Phases II and III. In Phase I, a literature review was conducted on relevant research and the current state of practice related to the evaluation of systems, including sign supports, breakaway poles, and work-zone traffic control devices, according to MASH 2016. The literature was synthesized and reviewed to identify knowledge gaps regarding the implementation of MASH related to systems. A plan for analytical and physical testing programs was proposed to address these knowledge gaps. Additionally, areas of MASH were identified for potential modification, and a preliminary outline for the guidelines was provided. Finally, Interim Report No. 1 was provided on March 1, 2021, and documented all efforts encompassing Phase I (Asadollahi Pajouh et al. 2021). A research summary was presented at a virtual meeting between the research team and the panel members at the conclusion of Phase I.
Per the approval of Phase I efforts and Interim Report No. 1, the research team proceeded with Phase II of this project. Based on the panel’s feedback during the meeting held on March 31, 2021, considering the available time and budget as well as ongoing relevant projects, the two most common families of devices were recommended by the research team and approved by the panel. These two families of devices were: (1) a steel luminaire pole with an aluminum TB1-17 frangible transformer base and (2) a single 2¼-in., 12-gauge PSST sign support. To optimize efficiency, the research team proposed analyzing the two families of devices simultaneously, with Midwest Roadside Safety Facility (MwRSF) focusing on the luminaire pole with a TB1-17 base and George Mason University (GMU) focusing on the single 2¼-in., 12-gauge PSST sign
support. The analysis of the luminaire pole would not depend on the analysis of the PSST sign support.
After the panel’s review and NCHRP approval of the Phase I efforts, the research team addressed the panel’s comments, submitted the revised Interim Report No. 1, and initiated Phase II of the project, which consisted of simulation and analytical evaluation of the two systems selected in Phase I.
In Phase I of this project, the research team proposed a definition of “family of devices,” as described previously. Two systems were selected for further evaluation:
In Phase II, the available crash tests were used for simulation validation. Regarding the luminaire pole, only two pendulum tests were available during Phase II. Later, two full-scale crash tests were performed at the Federal Outdoor Impact Laboratory (FOIL) and used for validation of the luminaire pole and transformer base models. For the PSST sign support, sign support systems that were developed and validated under NCHRP Project 03-119 were used as the starting point. Additional full-scale crash tests were identified from the literature and used for model validation. Following the validation of the models to the best possible extent, comprehensive simulations were conducted on various variations of the selected device families. The simulation results were used to identify critical cases, as was detailed in Interim Report No. 2 of this project (Asadollahi Pajouh et al. 2022). Based on the simulation results and observed trends, recommendations were made for the testing plan in Phase III, as summarized in Tables 7 and 8. Based on the updated simulation results, nine and seven full-scale crash tests were recommended for the family of luminaire poles with the TB1-17 transformer base and the family of single 2¼-in. by 12-ga. PSST sign supports, respectively.
Finally, after the submission and review of Interim Report No. 2, a teleconference was held between the research team and the project panel (Asadollahi Pajouh et al. 2022).
In Phase III, according to the original project plan, two full-scale crash tests were anticipated to be conducted at MwRSF, and five to eight full-scale crash tests were anticipated to be conducted at GMU and FOIL. Based on the simulations, the research team recommended nine full-scale crash tests on luminaire poles and seven full-scale crash tests on PSST sign supports.
Considering the costs associated with conducting full-scale crash tests, the full set of recommended crash tests deemed necessary to validate the simulations and prove the methodology
Table 7. Updated recommendations for Phase III full-scale crash testing – luminaire pole with TB1-17 transformer base.
| Sim. No. | Pole Height (ft) | Mast Arm Length (ft) | Mast Config. [Single (S), Double (D)] | Weight (lb) | MASH Test No. 3-60 | MASH Test No. 3-61 | MASH Test No. 3-62 | |||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Left 1/4 |
Center | Right 1/4 |
Left 1/4 |
Center | Right 1/4 |
Left 1/4 |
Center | Right 1/4 |
||||||||||||||
| 0 | 25 | 0 | 25 | 0 | 25 | 0 | 25 | 0 | 25 | 0 | 25 | 0 | 25 | 0 | 25 | 0 | 25 | |||||
| 1 | 20 | 4 | S | 259 | ||||||||||||||||||
| 54 | 20 | 4 | D | 374 | 4 | |||||||||||||||||
| 6 | 20 | 15 | S | 305 | ||||||||||||||||||
| 59 | 20 | 15 | D | 467 | 3 | 7 | 8 | |||||||||||||||
| 9 | 20 | 30 | S | 552 | ||||||||||||||||||
| 19 | 30 | 4 | S | 471 | ||||||||||||||||||
| 72 | 30 | 4 | D | 587 | 9 | |||||||||||||||||
| 24 | 30 | 15 | S | 518 | ||||||||||||||||||
| 77 | 30 | 15 | D | 679 | ||||||||||||||||||
| 27 | 30 | 30 | S | 763 | 2 | |||||||||||||||||
| 35 | 40 | 4 | S | 694 | ||||||||||||||||||
| 88 | 40 | 4 | D | 810 | ||||||||||||||||||
| 40 | 40 | 15 | S | 741 | ||||||||||||||||||
| 93 | 40 | 15 | D | 902 | ||||||||||||||||||
| 41 | 40 | 20 | S | 805 | ||||||||||||||||||
| 94 | 40 | 20 | D | 1,032 | ||||||||||||||||||
| 48 | 50 | 4 | S | 984 | ||||||||||||||||||
| 101 | 50 | 4 | D | 1,100 | 1* | 5 | 6 | |||||||||||||||
| 53 | 50 | 15 | S | 1,030 | ||||||||||||||||||
| 106 | 50 | 15 | D | 1,192 | ||||||||||||||||||
* Represents a recommended crash test; the numbers 1 to 9 denote the test priority.
for defining the two families of systems could not be conducted with the available funds. Thus, the research team recommended the following two options for continuing the project:
Following a review of the proposed recommendations, the panel decided that the research team should proceed with Option 2. Thus, the research team continued with two and five full-scale crash tests recommended for the families of the luminaire pole with TB1-17 transformer base and a single 2¼-in. by 12-ga. PSST sign support, respectively.
Table 8. Recommendations for full-scale crash testing in Phase III – single 2¼-in. by 12-ga. PSST sign support.
| Impact Condition | Panel Size | 1’ × 1.5’ | 2’ × 2’ | 2.5’ × 2.5’ | 3’ × 3’ | 3’ × 4’ | 4’ × 5’ | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Panel Thickness | 0.08 | 0.10 | 0.12 | 0.08 | 0.10 | 0.12 | 0.08 | 0.10 | 0.12 | 0.08 | 0.10 | 0.12 | 0.08 | 0.10 | 0.12 | 0.08 | 0.10 | 0.12 | |
| MASH 3-60 | Center/0 Deg. | ||||||||||||||||||
| Driver-Side Offset/0 Deg. | |||||||||||||||||||
| Pass.-Side Offset/0 Deg. | Test 1 | ||||||||||||||||||
| MASH 3-61 | Center/0 Deg. | ||||||||||||||||||
| Center/–5 Deg. | |||||||||||||||||||
| Center/+25 Deg. | |||||||||||||||||||
| Driver-Side Offset/0 Deg. | Test 3 | Test 6 | Test 2 | ||||||||||||||||
| Pass.-Side Offset/0 Deg. | |||||||||||||||||||
| MASH 3-62 | Center/0 Deg. | Test 5 | Test 7 | Test 4 | |||||||||||||||
| Center/+25 Deg. | |||||||||||||||||||
| Center/–25 Deg. | |||||||||||||||||||
Notes:
= meets MASH criteria;
= does not meet MASH criteria.
Data from these tests were used to validate or modify the LS-DYNA simulations, develop guidelines according to the approved outlines, and propose modifications to MASH. Finally, Interim Report No. 3 was assembled documenting all Phase III research efforts, and a research summary was presented at an in-person meeting between the research team and the panel members at the conclusion of Phase III. A breakdown of the individual tasks within Phase III is shown here:
Upon the project panel’s approval of the Phase III interim report and draft guidelines, the draft guidelines were provided, and the final report was revised according to panel members’ comments. The panel members reviewed the final deliverables, and their comments were incorporated into the final deliverables. A breakdown of the individual tasks within Phase IV is shown here:
This report is organized as follows:
The report also has several appendices that provide details related to the two families of devices studied under the project. These appendices can be found on the National Academies Press website (nap.nationalacademies.org) by searching for NCHRP Web-Only Document 405: Evaluating Crashworthiness of Sign Supports and Breakaway Luminaire Poles: Appendices.